Editorial backlog clearance time calculator

Estimate weeks to clear a publishing backlog while new work continues arriving.

Embed this calculator

Paste this into a Custom HTML block on your website. It uses the same calculator, with a link to this page for the method and examples. No account or publisher-side script is needed.

The frame starts at 720 pixels high and can scroll. You can change its height. Widget inputs stay inside the frame.

What the result means

Completing ten assignments a week while adding five clears only five existing assignments each week. A backlog of 100 therefore needs 20 weeks, not ten. A backlog of 20 with eight completions and three new assignments per week needs four weeks.

Worked examples

Illustrative inputs and calculated results
Input or resultExampleSecond example
Unfinished assignments10020
Assignments completed per week108
New assignments added per week53
Weeks needed to clear the backlog20 weeks4 weeks
Formula and input definitions

Weeks to clear = current backlog ÷ (weekly completed work − weekly incoming work), rounded up. Completion must exceed incoming work.

Unfinished assignments
Assignments in the backlog under a consistent readiness definition.
Assignments completed per week
Sustainable completion capacity at the current quality standard.
New assignments added per week
Expected inflow while the backlog is being cleared.

Limits and common mistakes

Completion capacity must exceed incoming work or the backlog does not shrink. Variable assignment size and partial completion are not modeled; use comparable units.